上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 7 Schedule Control

上浒充通大学 SHANGHAI JIAO TONG UNIVERSITY Project Management Dr.HU Hao 六漏 School of Naval Architecture Ocean and Civil Engineering Shanghai Jiao Tong University 2012
Project Management Dr. HU Hao School of Naval Architecture Ocean and Civil Engineering Shanghai Jiao Tong University 2012

图 上游充通大学 SHANGHAI JLAO TONG UNIVERSITY Part 2 PROJECT PLANNING AND CONTROL Chapter 7 Schedule Control
Part 2 PROJECT PLANNING AND CONTROL Chapter 7 Schedule Control

上游充通大粤 SHANGHAI JIAO TONG UNIVERSITY Learning Objectives Performing the steps in the project control process Determining the effects of actual schedule performance on the project schedule Incorporating project changes into the schedule Calculating an updated project schedule Controlling the project schedule
Learning Objectives Performing the steps in the project control process Determining the effects of actual schedule performance on the project schedule Incorporating project changes into the schedule Calculating an updated project schedule Controlling the project schedule

上游充通大粤 Project Control Process SHANGHAI JLAO TONG UNIVERSITY The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and taking corrective action immediately to get the project back on track. To keep track of which activities have been started and/or completed,when they were started and/or completed,and how much money has been spent or committed
The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and taking corrective action immediately to get the project back on track. To keep track of which activities have been started and/or completed, when they were started and/or completed, and how much money has been spent or committed. Project Control Process

上降充通大学 Project Control Process(Cont.) SHANGHAI JIAO TONG UNIVERSITY Project control process Establish baseline plan (schedule,budget) Wait until next report period 业 Start project During each report period Collect data on actual performance Incorporate changes into project plan (schedule,costs) (scope,schedule,budget) Calculate updated project schedule,budget,and forecasts Analyze current status compared to plan Are corrective Identify corrective actions needed? actions and Yes incorporate associated changes
Project control process Project Control Process (Cont.) Establish baseline plan (schedule, budget) Start project During each report period Wait until next report period Collect data on actual performance (schedule, costs) Incorporate changes into project plan (scope, schedule, budget) Calculate updated project schedule, budget, and forecasts Analyze current status compared to plan Are corrective actions needed? Identify corrective actions and incorporate associated changes Yes

上浒充通大鼻 SHANGHAI JIAO TONG UNIVERSITY Project Control Process(Cont.) A regular reporting period should collect: Data on actual performance Information on any changes in scope,schedule,and budget ④Keep in mind: Data should be collected in a timely manner and used to update the schedule and budget Compare updated schedule and budget to the baseline and analyze
Project Control Process (Cont.) A regular reporting period should collect: • Data on actual performance • Information on any changes in scope, schedule, and budget Keep in mind: • Data should be collected in a timely manner and used to update the schedule and budget • Compare updated schedule and budget to the baseline and analyze

上海充通大学 SHANGHAI JIAO TONG UNIVERSITY Project Control Process(Cont.) Project management is a proactive approach to controlling a project,to ensure that the project objective is achieved even when things don't go according to the plan. This third phase ends,when the requirements have been met, project objective has been accomplished, and the customer is satisfied
Project Control Process (Cont.) Project management is a proactive approach to controlling a project, to ensure that the project objective is achieved even when things don’t go according to the plan. This third phase ends, when • the requirements have been met, • project objective has been accomplished, • and the customer is satisfied

上游充通大学 Effects of Actual Schedule Performance SHANGHAI JIAO TONG UNIVERSITY Actual progress-whether faster or slower than planned- will have an effect on the schedule of the remaining, uncompleted activities of the project. Actual finish times(AFs)of completed activities will determine the earliest start and earliest finish times for the remaining activities in the network diagram,as will as the total slack
Effects of Actual Schedule Performance Actual progress — whether faster or slower than planned — will have an effect on the schedule of the remaining, uncompleted activities of the project. Actual finish times (AFs) of completed activities will determine the earliest start and earliest finish times for the remaining activities in the network diagram, as will as the total slack

上克通大Effects of Actual Schedule Performance(Cont.) SHANGHAI JIAO TONG UNIVERSITY Example: Remove old Patch Put up new wallpaper walls wallpaper 1 7 2 5 3 3 Required completion 20 days Remove old Patch Put up new wallpaper walls wallpaper 1 7 AF=10 2 5 3 3 Required completion 20 days
Effects of Actual Schedule Performance (Cont.) Example: Remove old wallpaper 1 - 7 Patch walls 2 - 5 Put up new wallpaper 3 - 3 Required completion = 20 days Remove old wallpaper 1 - 7 Required completion = 20 days AF = 10 Patch walls 2 - 5 Put up new wallpaper 3 - 3

上游充通大学 SHANGHAI JIAO TONG UNIVERSITY Incorporating Project Changes into the Schedule Changes represent revisions to the original project scope and will have an impact on the schedule and cost. 国 The degree of impact may depend on when the changes are requested. When the customer request a change,impact on the project should be estimated
Incorporating Project Changes into the Schedule Changes represent revisions to the original project scope and will have an impact on the schedule and cost. The degree of impact may depend on when the changes are requested. When the customer request a change, impact on the project should be estimated
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 6 Scheduling.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 5 Planning.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 4 The Project.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 3 Proposed Solutions.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 2 Needs Identification.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 13 Types of Project Organizations.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 12 Project Communication and Documentation.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 11 The Project Team.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 10 The Project Manager.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源_课程教学大纲.doc
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 1 Project Management Concepts.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)0 Introduction.pptx
- 上海交通大学:《SCM 供应链管理》教学资源_教学案例_Meditech Surgical.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class3_Process View of the Organization.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class2_Operations Strategy and Competitiveness.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class2_Introduction to Operations Management.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class1_课程大纲.pdf
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 佳华案例分析.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 Dewey订书机公司运营咨询报告——建华运营咨询公司.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 上海延锋分阶段实施及时供货.ppt
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 8 Resource Considerations.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 9 Cost Planning and Performance.pptx
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业活动的经济环境.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)组织的结构和运作.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)激励与组织成员的需要.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业决策的法律约束.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)课程简介(武邦涛)、企业活动的性质与布局.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业的目标与社会的需求.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)宗教文化类旅游资源.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游环境容量.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游区区位及建筑空间布局.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游总体规划及路线设计.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)课程简介(武邦涛)、旅游规划概述.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游资源和旅游区.ppt
- 上海交通大学:《旅游法规》课程教学资源(PPT讲稿)旅行社法律制度.ppt
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap06 Scheduling in Supply Chain Management.pdf
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第一章 企业以及企业管理基础知识(武邦涛).ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第二章 现代企业战略管理.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第三章 市场营销管理基础.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第四章 财务管理.ppt