上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 6 Scheduling

上浒充通大学 SHANGHAI JIAO TONG UNIVERSITY Project Management Dr.HU Hao 六漏 School of Naval Architecture Ocean and Civil Engineering Shanghai Jiao Tong University 2012
Project Management Dr. HU Hao School of Naval Architecture Ocean and Civil Engineering Shanghai Jiao Tong University 2012

图 上游充通大学 SHANGHAI JLAO TONG UNIVERSITY Part 2 PROJECT PLANNING AND CONTROL Chapter 6 Scheduling
Part 2 PROJECT PLANNING AND CONTROL Chapter 6 Scheduling

上游充通大粤 SHANGHAI JIAO TONG UNIVERSITY Learning Objectives Estimating the duration for each activity Establishing the estimated start time and required completion time for the overall project Calculating the earliest times at which each activity can start and finish,based on the project's estimated start time Calculating the latest times by which each activity must start and finish in order to complete the project by its required completion time Determining the amount of positive or negative slack between the time each activity can start or finish and the time it must start or finish Identifying the critical(longest)path of activities
Learning Objectives Estimating the duration for each activity Establishing the estimated start time and required completion time for the overall project Calculating the earliest times at which each activity can start and finish, based on the project’s estimated start time Calculating the latest times by which each activity must start and finish in order to complete the project by its required completion time Determining the amount of positive or negative slack between the time each activity can start or finish and the time it must start or finish Identifying the critical (longest) path of activities

上游充通大学 Activity Duration Estimates SHANGHAI JIAO TONG UNIVERSITY The first step in establishing a project schedule is to estimate the duration of each activity Estimated duration should include the time required to perform the work plus any associated waiting time Representation in the network AlB:in the lower-right-hand corner of the box AOA:below the arrow Activity Description of activity Description Person in Estimated 入 Duration Number charge duration Estimate Event Event Number Number
The first step in establishing a project schedule is to estimate the duration of each activity Estimated duration should include the time required to perform the work plus any associated waiting time Representation in the network • AIB: in the lower-right-hand corner of the box • AOA: below the arrow Activity Duration Estimates Description of activity Number Person in charge Estimated duration Activity Description Duration Estimate Event Number Event Number

上浒充通大粤 Activity Duration Estimates(Cont.) SHANGHAI JIAO TONG UNIVERSITY Who will estimate the activity duration The person who will perform the activity Experienced individual makes estimates for all the activities for which the organization or subcontractors is responsible Estimates should be based resource available Estimates should be aggressive and realistic Delays and accelerations will ten to cancel one another out Duration of dummy activities is 0
Activity Duration Estimates (Cont.) Who will estimate the activity duration • The person who will perform the activity • Experienced individual makes estimates for all the activities for which the organization or subcontractors is responsible Estimates should be based resource available Estimates should be aggressive and realistic Delays and accelerations will ten to cancel one another out Duration of dummy activities is 0

上游充通大粤 Project Start and Finish Time SHANGHAI JIAO TONG UNIVERSITY Estimated start time Required completion time The project's required completion time is normally a part of the project objective and stated in the contract Sometimes the overall project time is stated in terms of a cycle time rather than a specific calendar time Estimated start time can be defined as 0
Project Start and Finish Time Estimated start time Required completion time The project’s required completion time is normally a part of the project objective and stated in the contract Sometimes the overall project time is stated in terms of a cycle time rather than a specific calendar time Estimated start time can be defined as 0

上游充通大粤 Schedule Calculations SHANGHAI JLAO TONG UNIVERSITY The earliest times at which each activity can start and finish, based on the project's estimated start time. The latest times by which each activity must start and finish in order to complete the project by its required completion time
Schedule Calculations The earliest times at which each activity can start and finish, based on the project’s estimated start time. The latest times by which each activity must start and finish in order to complete the project by its required completion time

图 上游充通大粤 Earliest Start and Finish Time SHANGHAI JLAO TONG UNIVERSITY Earliest Start Time ES-the earliest time at which a particular activity can begin Earliest Finish Time EF-the earliest time at which a particular activity can be completed EF=ES+Duration Estimate
Earliest Start and Finish Time Earliest Start Time ES — the earliest time at which a particular activity can begin Earliest Finish Time EF — the earliest time at which a particular activity can be completed EF = ES + Duration Estimate

上游充通大学 SHANGHAI JIAO TONG UNIVERSITY Earliest Start and Finish Time(Cont.) Calculating forward Working through the network diagram from the beginning of project to the end of the project. ©Rule1 The earliest start time for a particular activity must be the same as or later than the latest of all the earliest finish time of all the activities leading directly into that particular activity
Earliest Start and Finish Time (Cont.) Calculating forward • Working through the network diagram from the beginning of project to the end of the project. Rule 1 • The earliest start time for a particular activity must be the same as or later than the latest of all the earliest finish time of all the activities leading directly into that particular activity

上游充通大粤 SHANGHAI JIAO TONG UNIVERSITY Earliest Start and Finish Time(Cont.) Example: Textbook Page 164/FIGURE 6.6 Textbook Page 166/FIGURE 6.7
Earliest Start and Finish Time (Cont.) Example: • Textbook Page 164 / FIGURE 6.6 • Textbook Page 166 / FIGURE 6.7
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 5 Planning.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 4 The Project.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 3 Proposed Solutions.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 2 Needs Identification.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 13 Types of Project Organizations.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 12 Project Communication and Documentation.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 11 The Project Team.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 10 The Project Manager.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源_课程教学大纲.doc
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 1 Project Management Concepts.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)0 Introduction.pptx
- 上海交通大学:《SCM 供应链管理》教学资源_教学案例_Meditech Surgical.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class3_Process View of the Organization.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class2_Operations Strategy and Competitiveness.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class2_Introduction to Operations Management.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class1_课程大纲.pdf
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 佳华案例分析.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 Dewey订书机公司运营咨询报告——建华运营咨询公司.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 上海延锋分阶段实施及时供货.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析1.ppt
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 7 Schedule Control.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 8 Resource Considerations.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 9 Cost Planning and Performance.pptx
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业活动的经济环境.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)组织的结构和运作.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)激励与组织成员的需要.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业决策的法律约束.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)课程简介(武邦涛)、企业活动的性质与布局.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业的目标与社会的需求.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)宗教文化类旅游资源.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游环境容量.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游区区位及建筑空间布局.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游总体规划及路线设计.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)课程简介(武邦涛)、旅游规划概述.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游资源和旅游区.ppt
- 上海交通大学:《旅游法规》课程教学资源(PPT讲稿)旅行社法律制度.ppt
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap06 Scheduling in Supply Chain Management.pdf
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第一章 企业以及企业管理基础知识(武邦涛).ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第二章 现代企业战略管理.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第三章 市场营销管理基础.ppt