上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 9 Cost Planning and Performance

上浒充通大学 SHANGHAI JIAO TONG UNIVERSITY Project Management Dr.HU Hao 六漏 School of Naval Architecture Ocean and Civil Engineering Shanghai Jiao Tong University 2012
Project Management Dr. HU Hao School of Naval Architecture Ocean and Civil Engineering Shanghai Jiao Tong University 2012

上游充通大学 SHANGHAI JLAO TONG UNIVERSITY Part 2 PROJECT PLANNING AND CONTROL Chapter 9 Cost Planning and Performance
Part 2 PROJECT PLANNING AND CONTROL Chapter 9 Cost Planning and Performance

上游充通大粤 SHANGHAI JIAO TONG UNIVERSITY Learning Objectives Items to be considered when estimating cost Preparing a baseline budget Cumulating actual costs Determining the earned value of work performed Analyzing cost performance Forecasting project cost at completion Controlling project costs ④Managing cash flow
Learning Objectives Items to be considered when estimating cost Preparing a baseline budget Cumulating actual costs Determining the earned value of work performed Analyzing cost performance Forecasting project cost at completion Controlling project costs Managing cash flow

上游充通大粤 Project Cost Estimates SHANGHAI JIAO TONG UNIVERSITY Cost planning starts with the proposal. The cost section may include elements as the following: ·Labor ·Materials ● Subcontractors and consultants (if used) Equipment and facilities rental Travel ·Contingencies Cost estimates should be aggressive yet realistic
Project Cost Estimates Cost planning starts with the proposal. The cost section may include elements as the following: • Labor • Materials • Subcontractors and consultants (if used) • Equipment and facilities rental • Travel • Contingencies Cost estimates should be aggressive yet realistic

上游充通大粤 SHANGHAI JLAO TONG UNIVERSITY Project Budgeting Two steps: First,the project cost estimate is allocated to the various work packages in the project work breakdown structure. Second,the budget for each work package is distributed over the duration of the work package
Project Budgeting Two steps: First, the project cost estimate is allocated to the various work packages in the project work breakdown structure. Second, the budget for each work package is distributed over the duration of the work package

上游充通大粤 SHANGHAI JLAO TONG UNIVERSITY Project Budgeting Step 1:Allocating the Total Budgeted Cost Allocating total project costs for the various elements to the appropriate work packages will establish a total budgeted cost(TBC)for each work package. The approaches to establishing the TBC for each work package:top-down and bottom-up. When all budgets are summed,they cannot exceed the TBC
Step 1: Allocating the Total Budgeted Cost Allocating total project costs for the various elements to the appropriate work packages will establish a total budgeted cost (TBC) for each work package. The approaches to establishing the TBC for each work package: top-down and bottom-up. When all budgets are summed, they cannot exceed the TBC. Project Budgeting

上游充通大粤 SHANGHAI JLAO TONG UNIVERSITY Project Budgeting Step 2:Developing the Cumulative Budgeted Cost The second step is to distribute each TBC over the duration of its work package. A cost is determined for each period. The cumulative budgeted cost(CBC)is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time. The CBC is the baseline that will be used in analyzing the cost performance of the project
Step 2: Developing the Cumulative Budgeted Cost The second step is to distribute each TBC over the duration of its work package. A cost is determined for each period. The cumulative budgeted cost (CBC) is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time. The CBC is the baseline that will be used in analyzing the cost performance of the project. Project Budgeting

上游充通大粤 Determining Actual Cost SHANGHAI JIAO TONG UNIVERSITY Track actual cost by establishing a system to collect data on funds actually expended. Periodically assign a portion of the total committed cost to actual cost. Total actual and committed cost by work package for comparison to the cumulative budgeted cost. Cumulative actual cost(CAC)should be calculated
Determining Actual Cost Track actual cost by establishing a system to collect data on funds actually expended. Periodically assign a portion of the total committed cost to actual cost. Total actual and committed cost by work package for comparison to the cumulative budgeted cost. Cumulative actual cost (CAC) should be calculated

上游充通大学 SHANGHAI JIAO TONG UNIVERSITY Determining the Value of Work Performed Earned value (EV)is the value of the work actually performed. Determine earned value by collecting data on the percent complete for each work package. Convert this percentage to a dollar amount by multiplying the total budgeted cost of the work package by the percent complete
Determining the Value of Work Performed Earned value (EV) is the value of the work actually performed. Determine earned value by collecting data on the percent complete for each work package. Convert this percentage to a dollar amount by multiplying the total budgeted cost of the work package by the percent complete

上游充通大粤 Cost Performance Analysis Four Measures SHANGHAI JIAO TONG UNIVERSITY TBC(total budgeted cost) CBC(cumulative budgeted cost) CAC(cumulative actual cost) CEV(cumulative earned value) They are used to determine whether the project is being performed within budget and whether the value of the work performed is in line with the actual cost
Cost Performance Analysis Four Measures TBC (total budgeted cost) CBC (cumulative budgeted cost) CAC (cumulative actual cost) CEV (cumulative earned value) They are used to determine whether the project is being performed within budget and whether the value of the work performed is in line with the actual cost
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 8 Resource Considerations.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 7 Schedule Control.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 6 Scheduling.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 5 Planning.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 4 The Project.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 3 Proposed Solutions.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 2 Needs Identification.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 13 Types of Project Organizations.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 12 Project Communication and Documentation.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 11 The Project Team.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 10 The Project Manager.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源_课程教学大纲.doc
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)Chapter 1 Project Management Concepts.pptx
- 上海交通大学:《工程项目管理 Engineering Project Management》教学资源(PPT课件)0 Introduction.pptx
- 上海交通大学:《SCM 供应链管理》教学资源_教学案例_Meditech Surgical.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class3_Process View of the Organization.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class2_Operations Strategy and Competitiveness.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class2_Introduction to Operations Management.pdf
- 上海交通大学:《运营管理 Operations Management》教学资源_Class1_课程大纲.pdf
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 佳华案例分析.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业活动的经济环境.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)组织的结构和运作.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)激励与组织成员的需要.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业决策的法律约束.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)课程简介(武邦涛)、企业活动的性质与布局.ppt
- 上海交通大学:《旅游企业经营决策》教学资源(PPT课件)企业的目标与社会的需求.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)宗教文化类旅游资源.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游环境容量.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游区区位及建筑空间布局.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游总体规划及路线设计.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)课程简介(武邦涛)、旅游规划概述.ppt
- 上海交通大学:《旅游开发与规划》教学资源(PPT课件)旅游资源和旅游区.ppt
- 上海交通大学:《旅游法规》课程教学资源(PPT讲稿)旅行社法律制度.ppt
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap06 Scheduling in Supply Chain Management.pdf
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第一章 企业以及企业管理基础知识(武邦涛).ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第二章 现代企业战略管理.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第三章 市场营销管理基础.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第四章 财务管理.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第五章 人力资源管理.ppt
- 上海交通大学:《管理基础》教学资源PPT课件(企业管理基础)第六章 项目管理.ppt