《物流系统分析与优化》课程教学课件(PPT讲稿)Quay Crane Scheduling

Quay Crane Scheduling
Quay Crane Scheduling

Quay Crane Scheduling with Non-lnterferenceconstraints Problem (QCSNiP) for single containervessel·Assumptions:Quay cranes are on the same track and thus cannot cross over each other.: Only one quay crane can work on a hold at a time until it completes the hold.:Compared with processingtimeof a hold bya quay crane, travel time of aquay cranebetween two holds is small and hence it is ignored
Quay Crane Scheduling with Non-Interference constraints Problem (QCSNIP) for single container vessel • Assumptions • Quay cranes are on the same track and thus cannot cross over each other. • Only one quay crane can work on a hold at a time until it completes the hold. • Compared with processing time of a hold by a quay crane, travel time of a quay crane between two holds is small and hence it is ignored

Land sideQuay-KcraneThe front of theThetailofthecontainervesselcontainervessel2H1H-1HoldContainervesselSea sideK:Thenumber ofquaycranesH:Thenumberof holds

ParametersKthe number ofquay cranes;Hthe number of holds:theprocessingtimeof hold hbya quay crane(l≤h<H);PhMa sufficientlylarge positive constantnumber
Parameters

Decision variablesXh.k1,if holdh ishandledbyquaycranek,O,otherwise(1≤h<H,1<k<K);Yh.nI, if hold h finishes no later than hold h'starts;O,otherwise(l≤h,h'≤H);Chthecompletiontimeofholdh(l<h≤H)
Decision variables

(1)maxChhSubject to:(2)VI0VI≤h,h≤H(5)Ch-(CH-PH)-(1-YhR)M≤0VI≤h,h≤HKKM(YHH+YRA)≥EKXhK-iX+1(6)VI≤h<h≤Hk=1(7)X,Y=oorIVl≤h,H≤H,VI<k≤K

The objective function (l)minimizes the makespan of handling one single container vessel, which is the latestcompletion timeamongall holds.Constraints (2)definetheproperty of thedecision variable Ch.Constraints(3)ensurethat everyholdmustbeperformedonlybyonequaycrane.Constraints(4)and(5)definetheproperties ofdecisionvariables Yh.w:Constraints (4)indicate thatYh,= if C,≤Cw-pw,whichmeans Yh=1when hold h finishes no later than hold h'starts; Constraints (5)indicate that Yh=0 if Ch>Cw-Pw,whichmeans Yh=O when hold h finishes after hold h'starts.Finally,the interference between quay cranes can beavoided by imposing Constraints(6).Suppose thatholds hand h'areperformed simultaneouslyand h<h',then this means that Yhu + Yw',h = o. Note that both quay cranes and holds are arranged in an increasing or-der from the front to the tail of the container vessel.Thus, if quay crane k handles hold h and quay crane!handlesholdh,thenk+I≤l

.Theproposed QcsNiP isproved to beNP-complete,meaningthatthere exists no polynomial time algorithm for its exact solution
• The proposed QCSNIP is proved to be NP-complete, meaning that there exists no polynomial time algorithm for its exact solution

GA·Solutionrepresentation:Intheformofchromosomerepresentingthesequenceofholds:A procedure is needed to develop the correspondingquay crane schedule
GA • Solution representation • In the form of chromosome representing the sequence of holds • A procedure is needed to develop the corresponding quay crane schedule

Step l:Based on the current position of each quay crane,determine which quay cranes can handlethe firstunassigned hold in the chromosome without interference with the other quay cranes.If there is onlyonequay crane available, this hold is assigned to this quaycrane.Then, this hold is deleted from thechromosome, and the position and the completion time of the assigned quay crane are updated.Iftherearetwoquaycranesavailable,goto Step2.Step 2:Compare the completion time of the two available quay cranes to finish their assigned holds, andassign this hold to the quay crane with earlier completion time.Then,this hold is deleted fromthe chromosome, and the position and the completion time of the assigned quay crane are updated.Iftheircompletiontimeisequal,gotoStep3.Step3:Comparethe distancebetween thishold and thesetwoavailablequay cranes,and assign this hold tothe quay crane with the shorter distance. Then, this hold is deleted from the chromosome, and theposition and the completion time of the assigned quay crane are updated.If their distance is equal,goto Step4.Step 4:Assign this hold to the quay crane with the smaller number.Then, this hold is deleted from the chro-mosome, and the position and the completion time of the assigned quay crane are updated.Step5:Steps 1-4arerepeateduntil alltheholdsin thechromosomeareassigned
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 《物流系统分析与优化》课程教学课件(讲稿)Global Optimization Genetic Algorithms.pdf
- 《物流系统分析与优化》课程教学大纲 Logistics System Analysis and Optimization.pdf
- 《生产质量控制》课程教学课件(PPT讲稿)CH1 Introduciton Product Design and Development.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH3 Opportunity Planning.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH4 Product Planning.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH2 Development Processes and Organizations.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH5 Identifying Customer Needs.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH9 Concept Testing.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH8 Concept Selection.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH6 Product Specifications.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH7 Concept Generation.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH10 Product Architecture.pptx
- 《生产质量控制》课程教学课件(PPT讲稿)CH11 Industrial Design.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH13 Prototyping.ppt
- 《生产质量控制》课程教学课件(PPT讲稿)CH12 Design for Manufacturing.ppt
- 《政治经济学》课程教学资源(文献资料)中英文词汇对照表.doc
- 《政治经济学》课程教学资源(作业习题)政治经济学总习题集(无答案).doc
- 《商务谈判》课课程教学大纲.pdf
- 《商务谈判》课程教学资源(PPT课件,完整讲稿,共八章).ppt
- 《运筹学》课程教学资源(试卷习题)第3章 线性规划的对偶理论.ppt
- 《物流系统分析与优化》课程教学课件(PPT讲稿)Trucking Scheduling in Container Terminals.pptx
- 《物流系统分析与优化》课程教学课件(PPT讲稿)ACO-TS for VRPTW.pptx
- 《物流系统分析与优化》课程教学课件(PPT讲稿)Bullwhip Effect.pptx
- 《物流系统分析与优化》课程教学课件(PPT讲稿)Judgmental Forecasting.pptx
- 《物流系统分析与优化》课程教学课件(PPT讲稿)Ant Colony Optimization(ACO)and Real Version ACOR.pptx
- 《物流系统分析与优化》课程教学课件(PPT讲稿)Forecasting Methods For Seaonal Series.ppt
- 《物流系统分析与优化》课程教学课件(PPT讲稿)Data-based Forecasting.ppt
- 《国际营销管理》课程教学课件(PPT讲稿)第二讲 公司战略与营销战略——合作建立客户关系.ppt
- 《供应链系统设计与管理》课程教学大纲 Designing and managing the Supply Chain system(研究生).pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第10章 产品与供应链的协调设计.pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第8章 采购外包战略.pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第11章 服务供应链管理(introduction to service supply chain management).pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第9章 供应链风险管理.pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第6章 供应链集成化.pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第7章 供应链战略联盟.pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第5章 牛鞭效应(bullwhip effect).pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第4章 供应契约(supply contracts).pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第1章. 供应链管理概述 Introduction to supply chain Management(SCM).pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第3章 供应链网络规划.pdf
- 《供应链系统设计与管理》课程授课教案(讲义,研究生)第2章 库存管理与风险分担.pdf