上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_2010_PPC_Answers

生产计划与控制2010至2011学年第1学期试卷A答案 Answer 1 a)and b) Forecast Period Actual et (86+75)/2=80.5 3 72 +8.5 (75+72)/2=73.5 4 83 -9.5 etc 77.5 5 132 -54.5 107.5 6 65 42.5 98.5 ) 110 -11.5 c)MAD=25.3 MSE =1014.25 MAPE = =28.0757 Answer 2 入=280 c =2.40 K =45 I=.20 a)Q*= 2K (2)(45)(280) =229 (.2)(2.40) b)T=Q*/=229/280=.8179yrs.(=9.81 months) c)G*=V2Kh=N(2)(45)(280)(.2)2.40)=$109.98 d) 229 3 wks R 9.82m0s
生产计划与控制 2010 至 2011 学年第 1 学期试卷 A 答案 Answer 1 a) and b) Forecast Period Actual et (86 + 75)/2 = 80.5 3 72 +8.5 (75 + 72)/2 = 73.5 4 83 -9.5 etc 77.5 5 132 -54.5 107.5 6 65 42.5 98.5 7 110 -11.5 c) MAD = 25.3 MSE = 1014.25 MAPE = 100 1 n ei Di = 28.0757 Answer 2 = 280 c = 2.40 K = 45 I = .20 a) Q* = 2K h (2)(45)(280) (.2)(2.40) 229 b) T = Q*/ = 229/280 = .8179 yrs. (= 9.81 months) c) G* = 2Kh = (2)(45)(280)(.2)(2.40) = $109.98 d) 229 R 3 wks 9.82 mos

r=y=(280)(3/52)=16.15 r=16 units Answer 3 a)c0=.08-.03=.05 cu=.35-.08=.27 Critical ratio 27 =.84375 .05+.27 From the given distribution,we have: f() F(Q)_ 0 .05 .05 5 .10 .15 10 .10 .25 15 .20 .45 20 .25 .70 <----.84375 25 .15 .85 30 .10 .95 35 .05 1.00 Since the critical ratio falls between 20 and 25 the optimal is Q=25 bagels. b)The answers should be close since the given distribution appears to be close to the normal. c)u=xf(x)=(0)(.05)+(5)(.10)+...+(35)(.05)=18 σ2=∑x2f(x)-u2=402.5-(18)2=78.5 (2321032) 0= .36 =8.86 The z value corresponding to a critical ratio of.84375 is 1.01. Hence, Q*=0z+μ=(8.86)(1.01)+18=26.95~27
r = = (280)(3/52) = 16.15 r = 16 units Answer 3 a) c0 = .08 - .03 = .05 cu = .35 - .08 = .27 Critical ratio = .27 .05 .27 = .84375 From the given distribution, we have: Q f(Q) F(Q) 0 .05 .05 5 .10 .15 10 .10 .25 15 .20 .45 20 .25 .70 - - - - .84375 25 .15 .85 30 .10 .95 35 .05 1.00 Since the critical ratio falls between 20 and 25 the optimal is Q = 25 bagels. b) The answers should be close since the given distribution appears to be close to the normal. c) = xf(x) = (0)(.05) + (5)(.10) +...+(35)(.05) = 18 2 = x 2f(x) - 2 = 402.5 - (18) 2 = 78.5 = (2)(32)(1032) .36 = 8.86 The z value corresponding to a critical ratio of .84375 is 1.01. Hence, Q* = z + = (8.86)(1.01) + 18 = 26.95 ~ 27

Answer 4 k 1700/120/46 0.308 thousands of cookies per worker per day Cum Cum *Cum #Units #Units Forecast Forecast *Monthly Monthly *End Working /Workers /Workers Demand Demand #Min Product Product Inv. Month Days (000 (000) (000) (000) Workers (000) (000) (000 26 8.01 8.01 850 850 107 1105 1105 255 2 24 7.39 15.40 1260 2110 138 1020 2125 15 20 6.16 21.56 510 2620 122 850 2975 355 4 16 4.93 26.49 980 3600 136 680 3655 55 Total 680 *Note:These three columns assume a work force of 138 workers in every period a)Minimum constant work force =138 workers b)CH=100 CF=200 CI=0.1 per cookie per month Initial workers =100 Beg.inv.0 workers hired 138 -100 38 End inv.=680 Total cost of this plan is (100)(38)+(.1)(680,000)=$71,800 Answer 5 a) MRP calculations:component A Week 910 11 12 13 14 15 16 17 Gross reqts 200 200 80 80200 400400 400 Net req 200 200 80 80200 400 400 400 Time phased net reg 200 200 80 80200 400400 400 Planned order release 200 200 80 80200 400 400 400 b)MRP calculations:component B Week 910 11121314151617 Gross reqts. 1001004040100200200200 Net reqts. 10010040 40100200200200 Time phased net reqts.100100 4040100200 200200 Planned order release 100 100 4040 100 200200 200 c)MRP calculations:component C Week 78910111213141516
Answer 4 k = 1700/120/46 = 0.308 thousands of cookies per worker per day. Cum Cum *Cum #Units #Units Forecast Forecast *Monthly Monthly *End Working /Workers /Workers Demand Demand #Min Product Product Inv. Month Days (000 (000) (000) (000) Workers (000) (000) (000 1 26 8.01 8.01 850 850 107 1105 1105 255 2 24 7.39 15.40 1260 2110 138 1020 2125 15 3 20 6.16 21.56 510 2620 122 850 2975 355 4 16 4.93 26.49 980 3600 136 680 3655 55 Total 680 *Note: These three columns assume a work force of 138 workers in every period a) Minimum constant work force = 138 workers b) CH = 100 CF = 200 CI = 0.1 per cookie per month Initial # workers = 100 Beg. inv. = 0 # workers hired = 138 - 100 = 38 End inv. = 680 Total cost of this plan is (100)(38) + (.1)(680,000) = $71,800 Answer 5 a) MRP calculations: component A Week 9 10 11 12 13 14 15 16 17 Gross reqts 200 200 80 80 200 400 400 400 Net req 200 200 80 80 200 400 400 400 Time phased net req 200 200 80 80 200 400 400 400 Planned order release 200 200 80 80 200 400 400 400 b) MRP calculations: component B Week 8 9 10 11 12 13 14 15 16 17 Gross reqts. 100 100 40 40 100 200 200 200 Net reqts. 100 100 40 40 100 200 200 200 Time phased net reqts. 100 100 40 40 100 200 200 200 Planned order release 100 100 40 40 100 200 200 200 c) MRP calculations: component C Week 6 7 8 9 10 11 12 13 14 15 16

Planned order release-A 2002008080200400400400 Gross reqts.of c for A 2002008080200400400400 Net reqts.of c for A 2002008080200400400400 Time ph.n.reqts.of C for A 20020080 80200400400400 P.O.release of c for A 2002008080200400400400 Planned order release-B 100100 4040100200200200 Gross reqts of c for B 2002008080200400400400 Net reqts.of c for B 2002008080200400400400 Time ph.n.reqts of c for B 200 200 8080200400400400 P.0.release of C for B 200200 8080200400400400 0 P.O.release of C for A&B 200400280160280600800800400 Answer 6 a)SPT sequence minimizes mean flow time.It is 6-5-1-4-2-7-3. b)First order by EDD which is 1-2-5-3-4-7-6. Processing Completion Job Time Time Due Date 3 4 2 6 9 8 Stop. Place job 2 at the end of the current sequence. Processing Completion Job Time Time Due Date V 0 3 4 5 2 5 11 8 13 12 Stop. Place job 3 at the end of the current sequence
Planned order release-A 200 200 80 80 200 400 400 400 Gross reqts. of C for A 200 200 80 80 200 400 400 400 Net reqts. of C for A 200 200 80 80 200 400 400 400 Time ph.n.reqts. of C for A 200 200 80 80 200 400 400 400 P.O. release of C for A 200 200 80 80 200 400 400 400 Planned order release-B 100 100 40 40 100 200 200 200 Gross reqts of C for B 200 200 80 80 200 400 400 400 Net reqts. of C for B 200 200 80 80 200 400 400 400 Time ph. n. reqts of C for B 200 200 80 80 200 400 400 400 P.O. release of C for B 200 200 80 80 200 400 400 400 0 P.O. release of C for A&B 200 400 280 160 280 600 800 800 400 Answer 6 a) SPT sequence minimizes mean flow time. It is 6-5-1-4-2-7-3. b) First order by EDD which is 1-2-5-3-4-7-6. Processing Completion Job Time Time Due Date 1 3 3 4 2 6 9 8 * Stop. Place job 2 at the end of the current sequence. Processing Completion Job Time Time Due Date 1 3 3 4 5 2 5 11 3 8 13 12 * Stop. Place job 3 at the end of the current sequence

Processing Completion Job Time Time Due Date 1 3 3 4 5 3 夕 11 4 Y 9 15 7 16 21 6 1 17 25 *Stop The optimal sequence is 1-5-4-7-6-2-3 (or 1-5-4-7-6-3-2).Jobs 2 and 3 are tardy. c)The maximum lateness is minimized by EDD which is 1-2-5-3-4-7-6. d)The makespan is the sum of the processing times which is 31
Processing Completion Job Time Time Due Date 1 3 3 4 5 2 5 11 4 4 9 15 7 7 16 21 6 1 17 25 * Stop The optimal sequence is 1-5-4-7-6-2-3 (or 1-5-4-7-6-3-2). Jobs 2 and 3 are tardy. c) The maximum lateness is minimized by EDD which is 1-2-5-3-4-7-6. d) The makespan is the sum of the processing times which is 31
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap10 Project Scheduling.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap09 Just-in-time.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap08 Operations Scheduling.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap07 Production Planning.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap05 Inventory Control Subject to Unknown Demand.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap04 Inventory Control Subject to Known Demand.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap03 Aggregate Planning.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap02 Forecasting.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap01 Production System and Operations Strategy.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)About the bullwhip effect.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)Review_Class2.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)Review_Class1.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap11_Class3.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap11_Class2.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap11_Class1.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap10_Class3.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap10_Class2.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap10_Class1.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap09_Class2.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》课程教学资源(课件讲稿)chap09_Class1.pdf
- 上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_2010_PPC_Examination.doc
- 上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_2011_PPC_Answers.doc
- 上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_2011_PPC_Examination.doc
- 上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_试卷A(2012).doc
- 上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_试卷B(2012).doc
- 上海交通大学:《生产计划与控制 Production Planning and Control》教学资源_历年试卷_试卷C(2012).doc
- 上海交通大学:《质量管理学》教学资源_作业阅读材料 A Man of Duality.pdf
- 上海交通大学:《质量管理学》教学资源_质量管理学课件《ISO9000》族国际标准.pdf
- 上海交通大学:《质量管理学》教学资源_分类_质量管理学课件(质量管理的历史、演绎).pdf
- 上海交通大学:《运营管理》教学资源_阅读报告 The impact of supply chain management practices on competitive advantage and organizational performance.ppt
- 上海交通大学:《运营管理》教学资源_阅读报告_改变世界的机器.ppt
- 上海交通大学:《运营管理》教学资源_文献阅读_自然灾害下的紧急物流计划.ppt
- 上海交通大学:《运营管理》教学资源_文献阅读_21世纪企业竞争前沿——大规模定制模式下的敏捷产品开发.ppt
- 上海交通大学:《运营管理》教学资源_文献阅读_大规模定制.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析1 Dewey 钉书机公司运营解决方案.doc
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析1.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 上海延锋分阶段实施及时供货.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 Dewey订书机公司运营咨询报告——建华运营咨询公司.ppt
- 上海交通大学:《运营管理》教学资源_案例分析_案例分析 佳华案例分析.ppt
- 上海交通大学:《运营管理 Operations Management》教学资源_Class1_课程大纲.pdf