华中科技大学:《IT项目管理》(本科)(英文版)Topic:4 Project Time Management

IT Project management Topic: Project Time Management INSTRUCTOR: SHU LIU HIT SCHOOL OF SOFTWARE Fall 2005 All rights reserved
Topic: Project Time Management IT Project Management INSTRUCTOR: SHU LIU HIT SCHOOL OF SOFTWARE Fall 2005 All rights reserved

IT Projectmanagement Outline Importance of project Schedules Project Time management process Activity Definition Activity sequencing Activity duration estimating Schedule development Schedule control Project Time management
Project Time Management 2 Outline ◼ Importance of Project Schedules ◼ Project Time Management Process ◼ Activity Definition ◼ Activity sequencing ◼ Activity duration estimating ◼ Schedule development ◼ Schedule control IT Project Management

Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Average time overrun from 1995 CHAOS report was 222%, improved to 63% in 2001 study Time has the least amount of flexibility: it passes no matter what a Schedule issues are the main reason for conflicts on projects, especially during the second halfof projects Project Time management
Project Time Management 3 Importance of Project Schedules ◼ Managers often cite delivering projects on time as one of their biggest challenges ◼ Average time overrun from 1995 CHAOS report was 222%; improved to 63% in 2001 study ◼ Time has the least amount of flexibility; it passes no matter what ◼ Schedule issues are the main reason for conflicts on projects, especially during the second half of projects

onflict Intensity Over the Life of a Project 0.40 0.35 0.30 口 Schedules 0.25 Average口 Priorities Total Conflict 口 Manpower 0.20 D Technical opinions ■ Procedures 0.15 口Cost 口 Personality conficts 60.10 0.05 0.00 Project Early Phases Middle Phases End Phase Formation Project Time management
Project Time Management 4 Conflict Intensity Over the Life of a Project 0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 Project Formation Early Phases Middle Phases End Phases Conflict Intensity Schedules Priorities Manpower Technical opinions Procedures Cost Personality conflicts Average Total Conflict

Proiect Time Management processes Project time management involves the processes required to ensure timely completion of a project Processes include Activity definition Activity sequencing activity duration estimating Schedule development Schedule control Project Time management 5
Project Time Management 5 Project Time Management Processes ◼ Project time management involves the processes required to ensure timely completion of a project. ◼ Processes include: ◼ Activity definition ◼ Activity sequencing ◼ Activity duration estimating ◼ Schedule development ◼ Schedule control

aCtivity Definition Where do schedules come from? Defining activities Project schedules grow out of the basic document that Initiate a project Project charter includes start and end dates and budget information Scope statement and WBS help define what will be done Activity definition involves developing a more detailed wbs and supporting explanations to understand all the work to be done Project Time management 6
Project Time Management 6 Where Do Schedules Come From? Defining Activities ◼ Project schedules grow out of the basic document that initiate a project ◼ Project charter includes start and end dates and budget information ◼ Scope statement and WBS help define what will be done ◼ Activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done

aCtivity Definition Activity Definition npu Output 1. WBS 2. Scope Statement 3. Historicalinfo 1. All Activities 4. Constraints 2. Detailed description 5. Assumptions 3. Revised wbs Project Time management
Project Time Management 7 Activity Definition Input 1. WBS 2. Scope Statement 3. Historical info. 4. Constraints 5. Assumptions Output 1. All Activities 2. Detailed description 3. Revised WBS

aCtivity Sequencing Ctivity Sequencing Involves reviewing activities and determining dependencies Mandatory dependencies: inherent in the nature of the work, hard logic Discretionary dependencies: defined by the project team; soft logic External dependencies: involve relationships between project and non-project activities Project Time management
Project Time Management 8 Activity Sequencing ◼ Involves reviewing activities and determining dependencies ◼ Mandatory dependencies: inherent in the nature of the work; hard logic ◼ Discretionary dependencies: defined by the project team; soft logic ◼ External dependencies: involve relationships between project and non-project activities

r Activity Sequencing Project Network Diagrams a Project network diagrams are the preferred technique for showing activity sequencing a project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities Arrow Diagramming Method (ADM) Precedence Diagramming Method (PDM Project Time management
Project Time Management 9 Project Network Diagrams ◼ Project network diagrams are the preferred technique for showing activity sequencing ◼ A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities ◼ Arrow Diagramming Method (ADM) ◼ Precedence Diagramming Method (PDM)

r Activity Sequencing Arrow Diagramming Method (ADM) Also called activity-on-arTOw(AOa) project network diagrams a Activities are represented by arrows a Nodes or circles are the starting and ending pe oints of activities 2 E 5 B 3 Project Time management
Project Time Management 10 Arrow Diagramming Method (ADM) ◼ Also called activity-on-arrow (AOA) project network diagrams ◼ Activities are represented by arrows ◼ Nodes or circles are the starting and ending points of activities 1 2 3 4 5 A B C D E
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:3 Project Scope Management.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:2 Project The Project Management Context and Processes.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:1 Introduction to Project Management.ppt
- 深圳职业技术学院:《C语言程序设计》第九单元:共用体,枚举(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第八单元:结构体(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第八单元(3):指针与结构体(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第八单元(2):结构体数组(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第八单元(1):结构体变量的定义、引用、初始化(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第七单元:指针及其应用(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第七单元(4):指针数组(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第七单元(3):字符串指针(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第七单元(2):指针与数组(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第七单元(1):指针变量的定义和引用(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第六单元:函数(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第六单元(4):变量的作用域与存储类别(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第六单元(3):函数的嵌套调用和递归调用(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第六单元(2):函数的参数传递方式(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第六单元(1):函数基础(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第五单元:数组(乌云高娃).pdf
- 深圳职业技术学院:《C语言程序设计》第 5 单元(8):数组编程总结(乌云高娃).pdf
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:5 Project Cost Management.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:6 Project HR Management.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:7 Project Communication Management.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:8 Project Risk Management.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Topic:9 Project Procurement Management.ppt
- 华中科技大学:《IT项目管理》(本科)(英文版)Ten attributes of a good employee.doc
- 华中科技大学:《IT项目管理》(本科)(英文版)What makes a good manager.doc
- 《NFS报文分析》讲义.doc
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 8 Code Generation.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 8.1 Intermediate Code and Data.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 8.6 Code Generation in Commercial Compilers:Two Case Studies.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 5.1 Overview of Bottom-UpParsing.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 5.3 SLR(1)Parsing.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 4.1 Top-Down Parsing by Recursive-Descent.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 4.1 Top-Down Parsing byRecursive-Descent.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 1.1 Why? A Brief History.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 7.1 Memory Organization During Program Execution.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 7.4 Dynamic Memory.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 6.1 Attributes and AttributeGrammars.ppt
- 清华大学:《编译原理》课程教学资源_(英文译文)Chapter 6.3 The Symbol Table.ppt