《基础工程》课程PPT教学课件(英文讲稿)Chapter 04 Factors to consider in foundation design

Chapter 4 Factors to consider in foundation design
Chapter 4 Factors to consider in foundation design

4.1 Footing depth and spacing Footing should be carried below: The frost line -Zones of high volume change due to moisture fluctuation Topsoil or organic material ■Peat and muck Unconsolidated material 园 超
4.1 Footing depth and spacing ▪ Footing should be carried below: ▪ The frost line ▪ Zones of high volume change due to moisture fluctuation ▪ Topsoil or organic material ▪ Peat and muck ▪ Unconsolidated material

4.1 Footing depth and spacing When footings are to be placed adjacent to an existing structure,the line from the base of the new footing to the bottom edge of the existing footing should be 45 or less with the horizontal plane. From this requirement it follows that the distance m should be greater than the difference in elevation of the two footings,Z. If the new footing is lower than the exiting footing,there is a possibility that the soil may flow laterally from beneath the existing footing. This may increase the amount of excavation somewhat but,more importantly,may result in settlement cracks in the existing building
4.1 Footing depth and spacing ▪ When footings are to be placed adjacent to an existing structure, the line from the base of the new footing to the bottom edge of the existing footing should be 45°or less with the horizontal plane. ▪ From this requirement it follows that the distance m should be greater than the difference in elevation of the two footings, zf . ▪ If the new footing is lower than the exiting footing, there is a possibility that the soil may flow laterally from beneath the existing footing. ▪ This may increase the amount of excavation somewhat but, more importantly, may result in settlement cracks in the existing building

4.1 Footing depth and spacing If the soil is a sand one cannot excavate to a depth greater than that of the existing foundation. The excavation depth of a o-c soil is limited by the equation: 2c 9o 2 (SF)yK (SF)Y
4.1 Footing depth and spacing ▪ If the soil is a sand one cannot excavate to a depth greater than that of the existing foundation. ▪ The excavation depth of a φ-c soil is limited by the equation: ( ) (SF) q SF K c zf 2 0 = −

4.2 Displaced soil effects Soil is always displaced by installing a foundation. In the case of spread footings the displacement is the volume of the footing pad and negligible amount from the column resting on the footing. In the cases of the spread footing with basement and the mat foundation we should consider loss of a part of ysD when computing the net pressure increase from building
4.2 Displaced soil effects ▪ Soil is always displaced by installing a foundation. ▪ In the case of spread footings the displacement is the volume of the footing pad and negligible amount from the column resting on the footing. ▪ In the cases of the spread footing with basement and the mat foundation we should consider loss of a part of γsD when computing the net pressure increase from building

4.3 Net versus gross pressure: design soil pressures The beating-capacity equations are based on gross soil pressure qut,which is everything above the foundation level. Settlements are caused only by net increases in pressure over the existing overburden pressure. If the allowable pressure is based on the beating- capacity equations,the pressure is a gross pressure. If the allowable pressure is based on settlement considerations,it is a net pressure. If enough soil mass is removed to equalize the building mass and float the building on to the soil with little or no settlement.This is called a floating foundation
4.3 Net versus gross pressure: design soil pressures ▪ The beating-capacity equations are based on gross soil pressure qult, which is everything above the foundation level. ▪ Settlements are caused only by net increases in pressure over the existing overburden pressure. ▪ If the allowable pressure is based on the beatingcapacity equations, the pressure is a gross pressure. ▪ If the allowable pressure is based on settlement considerations, it is a net pressure. ▪ If enough soil mass is removed to equalize the building mass and float the building on to the soil with little or no settlement. This is called a floating foundation

4.4 Erosion problems for structures adjacent to flowing water Bridge pier,abutments,bases for retaining walls, and footings for other structures adjacent to or located in flowing water must be located at a depth such that erosion or scour does not undercut the soil and cause a failure. Scour occurs principally during floods,but some scour occur at other times;in either case a scour-out pit or depression)in the stream bed may result. Scour is accelerated if the foundation creates channel obstruction
4.4 Erosion problems for structures adjacent to flowing water ▪ Bridge pier, abutments, bases for retaining walls, and footings for other structures adjacent to or located in flowing water must be located at a depth such that erosion or scour does not undercut the soil and cause a failure. ▪ Scour occurs principally during floods, but some scour occur at other times; in either case a scour-out pit ( or depression) in the stream bed may result. ▪ Scour is accelerated if the foundation creates channel obstruction

4.5 Corrosion protection In polluted ground areas there can be corrosion problems with metal foundation members as well as with concrete. Concrete is normally resistant to corrosion; however,if sulfates are present,it may be necessary to use sulfate-resistant concrete. It may occasionally be necessary to use air- entrained concrete for foundation member. Steel piles are not suggested for use in sea water unless coated and not allowed to undergo wet-dry cycle. 阳喝
4.5 Corrosion protection ▪ In polluted ground areas there can be corrosion problems with metal foundation members as well as with concrete. ▪ Concrete is normally resistant to corrosion; however, if sulfates are present, it may be necessary to use sulfate-resistant concrete. ▪ It may occasionally be necessary to use airentrained concrete for foundation member. ▪ Steel piles are not suggested for use in sea water unless coated and not allowed to undergo wet-dry cycle

46 Water fable fluctuation -A lowered water table increases the effective pressure and may cause additional settlements. -A raised water table may create problems due to: 3 刷 超
4.6 Water table fluctuation ▪ A lowered water table increases the effective pressure and may cause additional settlements. ▪ A raised water table may create problems due to: ▪ ①~③

4.7 Foundations in sand and silt deposits Foundation on sand and silt will require consideration of the following: ■①~④ Foundation on silt or sand deposits may consist of spread footings,mats,or piles,depending on the density,thickness,and cost of densifying the deposit,and on the building loads. Rapid or immediate settlements occur on noncohesive silt or sand deposits
4.7 Foundations in sand and silt deposits ▪ Foundation on sand and silt will require consideration of the following: ▪ ①~④ ▪ Foundation on silt or sand deposits may consist of spread footings, mats, or piles, depending on the density, thickness, and cost of densifying the deposit, and on the building loads. ▪ Rapid or immediate settlements occur on noncohesive silt or sand deposits
按次数下载不扣除下载券;
注册用户24小时内重复下载只扣除一次;
顺序:VIP每日次数-->可用次数-->下载券;
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 03 Improving Site Soils for Foundation Use.ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 02 基础承载力 Bearing capacity of foundation(2/2).ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 02 基础承载力 Bearing capacity of foundation(1/2).ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 02 Bearing capacity of foundations.ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 10 Single Piles(2/2).ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 10 Single Piles(1/2).ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 01 Introduction.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)绪论(主讲:赵明华).ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第四章 桩基础.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第六章 基坑工程.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第八章 地基处理.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第五章 沉井基础.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第二章 刚性基础与扩展基础.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第三章 柱下条形基础、筏形和箱形基础.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第一章 地基基础设计原则.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第四章 桩基础的设计计算.ppt
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第六章 地基基础.ppt
- 长沙理工大学:《基础工程》课程电子教案(讲义)第六章 地基基础.doc
- 长沙理工大学:《基础工程》课程电子教案(PPT课件)第五章 沉井基础及地下连续墙.ppt
- 长沙理工大学:《基础工程》课程电子教案(讲义)第五章 沉井基础及地下连续墙.doc
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 05 Spread footing design.ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 06 Special footings and beams on the elastic foundations.ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 07 Mat Foundation.ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 08 Mechanically Stabilized Earth and Concrete Retaining Walls.ppt
- 《基础工程》课程PPT教学课件(英文讲稿)Chapter 09 Sheet-Pile Walls(Cantilevered and Anchored).ppt
- 《基础工程》课程教学资源(参考资料)中华人民共和国行业标准(JTG D61-2005)公路圬工桥涵设计规范.pdf
- 《基础工程》课程教学资源(参考资料)中华人民共和国行业标准(JTG D62-2004)公路钢筋混凝土及预应力混凝土桥涵设计规范 Code for Design of Highway Reinforced Concrete and Prestressed Concrete Bridges and Culverts.pdf
- 《基础工程》课程教学资源(参考资料)中华人民共和国行业标准(JTG D63-2007)公路桥涵地基及基础设计规范(报批初稿)Code for Design of Ground Base and Foundation of Highway Bridges and Culverts.pdf
- 同济大学:《有限元方法》课程教学资源(试卷习题)考核试卷(A卷)2011-2012学年第1学期(含解答).pdf
- 同济大学:《有限元方法》课程教学资源(试卷习题)WORKSHOP 10 SUPPORT BRACKET.pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 1 Finite Element Method - Introduction to Finite Element Method.pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 2 Stiffness Matrices, Spring and Bar Elements.pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 3 Direct Stiffness Method(DSM).pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 4 Flexure elements.pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 6 Interpolation Functions for General Element Formulation.pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 7 Isoparametric Element.pdf
- 同济大学:《有限元方法》课程教学资源(教案讲义)Chapter 8 Practical modeling Issues.pdf
- 北京化工大学:《过程设备设计》课程教学资源(课件讲稿)第四章 压力容器设计 Design of Pressure Vessels 4.3 常规设计 4.3.4 密封装置设计.pdf
- 上海海洋大学:工程学院2011年版课程教学大纲汇编(正文).pdf
- 上海海洋大学:食品学院2018年版课程教学大纲汇编(能源与动力、建筑环境专业).pdf